ML-1 Project to transform Pakistan Railways into a Modern, Efficient Transport Network

District


HYDERABAD:An important meeting was held at the HCSTSI Secretariat under the chairmanship of Hyderabad Chamber of Small Traders and Small Industry President Nadeem Ahmed Siddiqui, in which Pakistan Railways’ Main Line One (ML-1) Project Community Liaison and Stakeholder Consultation Specialist (PRF-C) Waheed Ahmed and Tanveer Ahmed gave a detailed briefing on the proposed project for upgrading and modernizing the railway corridor from Karachi to Rohri.



On this occasion, Waheed Ahmed said that the current system of Pakistan Railways is about 161 years old and historically the railway track laid from Karachi to Rohri has been one of the foundations of this system.



The Karachi to Rohri priority section will be upgraded and modernized under Main Line One. He said that this project is being taken forward under the Project Implementation Unit (PIU/CPEC) of Pakistan Railways with the financial assistance of the Asian Development Bank (ADB), while the process of preparing the detailed design is underway.



Giving technical details of the project, he said that along with upgrading the existing railway track according to modern requirements, an additional track will also be laid. The proposal includes strengthening the railway line, improving the track surface and raising it by about one meter, so that the journey of trains can be made safer, more comfortable and smoother and vibration can be reduced during the journey.



The briefing further informed that under the project, it is proposed to install safety barriers on both sides of the track to eliminate encroachments on railway land and prevent future encroachments.



Steps to eliminate inactive railway stations while upgrading active stations to improve facilities for passengers are also part of the project. In addition, a plan to include 130 new trains was also presented to make the operational system of the railway more effective.



According to Waheed Ahmed, the Karachi to Rohri priority section consists of about 481 kilometers. The detailed design of the project is targeted to be completed by December 2026 and practical work to start in 2027, while it is proposed to set a period of about six years for the overall completion of the project. He said that the project is being designed keeping in mind the long-term needs and according to the requirements of the next 100 years.



On this occasion, President Hyderabad Chamber Nadeem Ahmed Siddiqui said that Hyderabad Chamber will fully cooperate with the department to improve, modernize Pakistan Railways and make it in line with international standards. He said that the modern and effective railway system can play an important role in promoting the country’s commercial, industrial and economic activities, especially the improvement in freight and passenger travel facilities will also benefit the business community.



The President of the Chamber proposed that a joint working committee consisting of all the relevant trade bodies of Sindh, including Hyderabad Chamber, be formed regarding this important project, which would present its suggestions and valuable opinions at different stages of the project and also review its progress as an observer.



The reports compiled by the committee should be sent to the relevant government authorities to help ensure quality, transparency and set goals during the implementation of the project.



During the meeting, the members of the chamber also asked questions regarding various technical, administrative and commercial aspects of the project, to which detailed answers were given.



The meeting was attended by Senior Vice President Muhammad Fahad Mian, Vice President Irfan Arbiani, Former President Muhammad Akram Ansari, Convener Railway Affairs Sheikh Ghulam Rasool, Executive Committee members Sikandar Ali Rajput, Sheikh Ahmed Hussain, Syed Faraz Ali Shah, Zaheeruddin Siddiqui, and other members Chaudhry Muhammad Aslam, Sohail Memon, Muhammad Al-Nasir.